Concrete Door Frames | |||
---|---|---|---|
System Components | Initial Cost Structure | ||
![]() |
![]() |
||
Critical Factors | Tools Used | ||
1. Curing 2. Quality of sand for concrete 3. Provision of holes at the right place for fixing door shutters 4. Holes for fixing the door shutter |
1. Trowel 2. Wooden float 3. Straight float |
||
DO'S | DON'T'S | ||
1. Frames should be cured for 14 days 2. Mortar should be used within 30 minutes of adding water to mix 3. Frames should be stacked properly |
1. Cavities should not be left in the frame during casting 2. Fine sand should not be used 3. Excess water should not be added to the concrete |
||
Construction Process | |||
Take measured quantities of cement, sand, and aggregates and mix the concrete![]() ![]() |
Clean and assemble the mould![]() ![]() |
Place reinforcement in the mould and fill concrete![]() ![]() |
Insert a PVC pipe at the center of the post to fix door latch![]() ![]() |
Compact the concrete with trowel to get uniform thickness to the framebr>
![]() ![]() |
Remove the mould![]() ![]() |
Finish the edges with straight edge![]() ![]() |
Finish the edges with wooden float![]() ![]() |
Clean the concrete from the PVC pipe provided for the door latch![]() ![]() |
Make hole on post to fix door hinges![]() ![]() |
Cure the frames for 14 days![]() ![]() |
Stack the frames![]() ![]() |
Erect RCC door frames in the house![]() ![]() |
A house with an RCC door frame![]() ![]() |
A House with RCC frame and wooden shutters![]() |